Neighborhood street improvement program 28 (NSIP 28)

Print
Press Enter to show all options, press Tab go to next option

Introduction

NSIP 28 outlines a list of roads that comprise 20% of the City’s total road infrastructure to be treated this year with either a slurry seal or microsurface treatment. The City plans to operate the slurry machine, resurfacing a few streets every week, for as long as the weather and other conditions permit. The city asks all residents that will be affected by the maintenance to check this page frequently for updates on the progress of NSIP 28.

Read the NSIP 28 METHODOLOGY page for a list of all of the streets slated to receive treatment.

Read our Slurry Frequently Asked Questions Page for answers to commonly asked questions about the slurry seal treatment.

If you have unanswered questions about NSIP 28, send an email to slurry@bullheadcity.com.

If you need to discuss an urgent matter related to NSIP 28, call (928)234-8752.

 

UPDATES/PROGRESS

The posted schedules for NSIP 28 are rough estimates only. There are a number of variables including weather conditions and equipment failure that can cause unexpected delays or changes in the schedule. The most up to date information will always be posted in this section of this page.

Update Tuesday June 6th

Maintenance scheduled for Monday June 5th was not completed due to weather and equipment failures. Maintenance for Monday, Tuesday, and Wednesday are being pushed back by one day to compensate. Maintenance scheduled for Thursday will be rescheduled for a later date.

Update Tuesday June 20th

Maintenance on Industrial Blvd for June 21st has been cancelled. There are no plans to reschedule.

Update Thursday May 11th

Scheduled Maintenance was added for Friday May 12th

Update Tuesday May 9th

Maintenance to Columbus Dr was added to the schedule for Thursday May 11th.

Update Thursday May 4th

The Coda Trail Morning side Drive in Ryan's way did not receive scheduled maintenance due to delays. Maintenance will be rescheduled to a later date.

 

This Week's Scheduled Maintenance

The City of Bullhead City Public Works Department will begin slurry seal/micro surface treatment on the following streets as a part of the 28th Neighborhood Street Improvement Program (NSIP 28): 

Monday June 19th

  • Newberry Dr from the intersection of Miracle Mile to the intersection of Arcadia Blvd

Tuesday June 20th

  • Booster Dr from the intersection of Miracle Mile heading East for 1130 feet

Wednesday June 21st - CANCELLED

  • Industrial Rd from the intersection of to the end of pavement

    The scheduled days are a target, and a number of factors can put city crews either ahead or behind schedule. Anyone who will be affected by this maintenance is highly encouraged to check the City’s website frequently at www.bullheadcity.com/nsip28 for the most up to date information. Anyone with concerns, comments, or questions about NSIP 28 should send an email to slurry@bullheadcity.com. Anyone with an urgent matter relating to NSIP 28 should call (928)234-8752.

     

    Next Week's Scheduled Maintenance

    SUBJECT TO CHANGE: Preliminary schedules for the upcoming week of Maintenance are typically formed the Wednesday before work is to begin. A more firm schedule is released the Friday before work is scheduled to begin. All schedules are targets that may or may not be met depending on factors such as weather and equipment failure.

      

    Map of NSIP 28

    2016-06-21_NSIP 28Read the full list of streets slated to be a part of NSIP 28 on the METHODOLOGY page.